Interior Demolition Cost

Interior Demolition Work Cost India Per Sq. Ft.

Home renovation starts with the demolition of existing things like brick wall, plaster, flooring and wall tiles etc. Which are charged on a per square foot basis by the civil contractors in Mumbai. Breaking of brick walls with different thickness are charged differently and also complex demolition work charged separately due to safety measures.

  • 4” / 6” / 9” wall breaking
  • Plaster removal
  • Tile removal (floor & wall)
  • RCC slab breaking
  • Hacking work
  • Kitchen platform dismantling
  • PCC floor removal
  • Granite frame breaking

4″ Brick Wall Breaking – Per Sq. Ft.

  • Mumbai – Rs.35 per sq. ft.

  • Navi Mumbai – Rs.30 per sq. ft.

  • Thane – Rs.30 per sq. ft.

  • Bhiwandi – Rs.25 per sq. ft.

  • Mira-Bhayandar – Rs.30 per sq. ft.

  • Vasai-Virar- Rs.25 per sq. ft.

  • Dombivli-Kalyan – Rs.25 per sq. ft.

  • Panvel – Rs.30 per sq. ft.

6″ Brick Wall Breaking – Per Sq. Ft.

  • Mumbai – Rs.40 per sq. ft.

  • Navi Mumbai – Rs.35 per sq. ft.

  • Thane – Rs.35 per sq. ft.

  • Bhiwandi – Rs.30 per sq. ft.

  • Mira-Bhayandar – Rs.35 per sq. ft.

  • Vasai-Virar- Rs.30 per sq. ft.

  • Dombivli-Kalyan – Rs.30 per sq. ft.

  • Panvel – Rs.35 per sq. ft.

9″ Brick Wall Breaking – Per Sq. Ft.

  • Mumbai – Rs.45 per sq. ft.

  • Navi Mumbai – Rs.40 per sq. ft.

  • Thane – Rs.40 per sq. ft.

  • Bhiwandi – Rs.40 per sq. ft.

  • Mira-Bhayandar – Rs.40 per sq. ft.

  • Vasai-Virar- Rs.35 per sq. ft.

  • Dombivli-Kalyan – Rs.35 per sq. ft.

  • Panvel – Rs.40 per sq. ft.

3D Design Interior Services

Wall Plaster Breaking – Per Sq. Ft.

  • Mumbai – Rs.35 per sq. ft.

  • Navi Mumbai – Rs.30 per sq. ft.

  • Thane – Rs.30 per sq. ft.

  • Bhiwandi – Rs.25 per sq. ft.

  • Mira-Bhayandar – Rs.30 per sq. ft.

  • Vasai-Virar- Rs.25 per sq. ft.

  • Dombivli-Kalyan – Rs.25 per sq. ft.

  • Panvel – Rs.30 per sq. ft.

Floor & Wall Tiles Breaking – Per Sq. Ft.

  • Mumbai – Rs.40 per sq. ft.

  • Navi Mumbai – Rs.35 per sq. ft.

  • Thane – Rs.35 per sq. ft.

  • Bhiwandi – Rs.30 per sq. ft.

  • Mira-Bhayandar – Rs.35 per sq. ft.

  • Vasai-Virar- Rs.30 per sq. ft.

  • Dombivli-Kalyan – Rs.30 per sq. ft.

  • Panvel – Rs.35 per sq. ft.

Tancha (Hacking) Work – Per Sq. Ft.

  • Mumbai – Rs.15 per sq. ft.

  • Navi Mumbai – Rs.10 per sq. ft.

  • Thane – Rs.10 per sq. ft.

  • Bhiwandi – Rs.10 per sq. ft.

  • Mira-Bhayandar – Rs.10 per sq. ft.

  • Vasai-Virar- Rs.10 per sq. ft.

  • Dombivli-Kalyan – Rs.10 per sq. ft.

  • Panvel – Rs.10 per sq. ft.

Kitchen Platform Breaking – Per Rft.

  • Mumbai – Rs.120 per Rft.

  • Navi Mumbai – Rs.100 per Rft.

  • Thane – Rs.100 per Rft.

  • Bhiwandi – Rs.100 per Rft.

  • Mira-Bhayandar – Rs.100 per Rft.

  • Vasai-Virar- Rs.100 per Rft.

  • Dombivli-Kalyan – Rs.100 per Rft.

  • Panvel – Rs.100 per Rft.

RCC Breaking – Per Sq. Ft.

  • Mumbai – Rs.75 per sq. ft.

  • Navi Mumbai – Rs.70 per sq. ft.

  • Thane – Rs.70 per sq. ft.

  • Bhiwandi – Rs.65 per sq. ft.

  • Mira-Bhayandar – Rs.70 per sq. ft.

  • Vasai-Virar- Rs.60 per sq. ft.

  • Dombivli-Kalyan – Rs.60 per sq. ft.

  • Panvel – Rs.70 per sq. ft.

Floor PCC Breaking – Per Sq. Ft.

  • Mumbai – Rs.40 per sq. ft.

  • Navi Mumbai – Rs.35 per sq. ft.

  • Thane – Rs.35 per sq. ft.

  • Bhiwandi – Rs.30 per sq. ft.

  • Mira-Bhayandar – Rs.35 per sq. ft.

  • Vasai-Virar- Rs.35 per sq. ft.

  • Dombivli-Kalyan – Rs.30 per sq. ft.

  • Panvel – Rs.35 per sq. ft.

Granite Frames Breaking – Per Rft

  • Mumbai – Rs.60 per Rft.

  • Navi Mumbai – Rs.50 per Rft.

  • Thane – Rs.50 per Rft.

  • Bhiwandi – Rs.50 per Rft.

  • Mira-Bhayandar – Rs.50 per Rft.

  • Vasai-Virar- Rs.50 per Rft.

  • Dombivli-Kalyan – Rs.50 per Rft.

  • Panvel – Rs.50 per Rft.

Note:-

  • All above rates are mentioned per square foot / running feet basis.

  • Above mentioned cost includes labor only.
  • Debris removal cost is not included in above rates.
  • Above mentioned cost may change as per site location and quantity of work.

  • Demolition work cost should be considered for the primary calculation only.

  • Take an accurate cost from a professional contractor after a site visit.